Notice: Function WP_Scripts::add was called incorrectly. The script with the handle "twentysixteen-script" was enqueued with dependencies that are not registered: jquery. Please see Debugging in WordPress for more information. (This message was added in version 6.9.1.) in /home/mcphillipsco/public_html/wp-includes/functions.php on line 6131

Travelodge Progress

McPhillips is seven months into programme and work is proceeding well on the £5.7m project to deliver a new 68 bed Travelodge hotel in Telford Town Centre. The structure has been completed, roof cladding is on and the first fix internal fit-out is proceeding. Bathroom pods have all been installed and the windows are due for fitting next week. We are also well underway with the enhanced public realm and the fountains are due to be installed shortly followed by feature seating areas.