McPhillips undertook this project to renew existing footway and public realm paving immediately adjacent to the Ironbridge, within the World Heritage Site. This is an extremely popular and very busy tourist attraction, and sensitively managing large volumes of pedestrians and vehicles while delivering a high-quality public realm were critical to the successful delivery of the scheme.
Paving works in isolated 50m areas were agreed in conjunction with the council. Temporary pedestrian and pushchair/wheelchair-friendly routes were provided when existing footpaths required short-term closures, and access to the frontages of local businesses — tearooms, gift shops and the like — was maintained throughout. Close liaison was achieved by the site agent through his constant presence on site and weekly visits to the owners and managers of the premises adjacent to the Wharfage.
3,015m² of existing Yorkstone paving was taken up from the footways and approaches to the Ironbridge and stored securely for return to the council. In its place McPhillips laid a Baggeridge clay paver grouted on mortar and sand beds. 60 existing cast-iron bollards, 15 waste bins and 160m of cast-iron kerbs were re-used, having been set aside during removal of the original paving.
In early 2017 Shropshire Council awarded McPhillips five highway improvement schemes to key junctions in Shrewsbury. The individual work…
The Iron Lane Junction Improvement Scheme was implemented to remove a major pinchpoint on the A4040 Outer Ring Road in Stechford,…
Wychavon District Council appointed McPhillips under a JCT Contract to deliver car park resurfacing and associated civil works in…