Broadway car park — completed McPhillips project

Broadway car park

Wychavon District Council·£90,000·Broadway, Worcestershire·8th January 2026 - 16th January 2026

Resurfacing the short-stay car park in Broadway.

Wychavon District Council appointed McPhillips under a JCT Contract to deliver car park resurfacing and associated civil works in Broadway, the gateway village to the Cotswolds and a major tourist destination.

The council required the short-stay car park to be resurfaced and issues with standing water resolved whilst maintaining the village’s reputation as a popular tourist destination. The project was completed during the quieter month of January to minimise disruption to the village.

The programme encompassed overlaying the entire car park, adjusting ironwork and kerbs, resetting wall coping stones, jetting and cleaning out gullies, and fully re-white-lining the car park. The client’s main concern was long-standing issues with standing water, all of which were fully resolved through the project.

40mm
Stone mastic asphalt overlay
7 days
Tight winter programme
0
Defects on handover

The challenge

The project presented significant challenges despite its relatively short duration. The live car park had to be closed in the very popular tourist village of Broadway, requiring careful management of public expectations and communication. A public right of way running through the centre of the car park required careful management throughout the project to ensure safety and minimise disruption to pedestrians.

Winter weather conditions severely impacted the works, with one full day lost due to snow and a further two days impacted by heavy, persistent rain, all whilst working to a tight seven-day programme. The combination of challenging weather and tight scheduling created significant pressure on the delivery team.

The high-profile nature of the village meant the project was under considerable public and political scrutiny, with concerns about disruption to the popular tourist destination during the works. Coordinating the closure of a heavily-used car park in a busy village required comprehensive communication and careful management of public expectations.

Broadway car park — The challenge
Before
Broadway car park — The solution

The solution

All works were carried out by McPhillips’ in-house civil engineering gangs and surfacing crew, ensuring full control over quality, programme and health & safety.

Working within a live and high-profile tourist village, careful planning of the car park closure was implemented alongside management of the public right of way through the site centre to ensure safety and minimise disruption.

To enhance communication with the public, McPhillips introduced a new QR code system on closure boards, allowing members of the public to access full closure information including design drawings directly via their smartphones. This innovative approach to stakeholder engagement demonstrated commitment to transparency and public engagement.

The programme was tightly managed to mitigate the impact of winter weather, with daily coordination between civil and surfacing teams to maximise productivity and maintain progress despite snow and persistent rain. This integrated approach enabled efficient delivery of works safely and to high standard.

Value engineering enhanced the project by overlaying the surface with 40mm stone mastic asphalt rather than simple re-laying, improving durability and performance whilst streamlining the programme. This adaptive approach allowed completion more efficiently whilst delivering a longer-lasting, higher-quality surface than originally specified.

“
Given the political nature of Broadway & how busy the car park gets with cars and pedestrians passing through, it’s been a great success to complete within the timescales agreed. A credit to everyone at McPhillips for a decent job.”
Jack Williams
Senior engineer, Wychavon District Council

The result

The project was successfully completed to a high standard, on time and within budget, and with zero defects. The client’s main concern regarding long-standing issues with standing water was fully resolved, delivering lasting improvements to the car park’s functionality.

The entire car park was successfully overlaid, ironwork and kerbs adjusted, wall coping stones reset, gullies jetted and cleaned, and the car park fully re-white-lined to high standards.

Broadway car park — The resultBroadway car park — The result — detail
Broadway car park — Before works
Broadway car park — Complete
Before works Complete

Project gallery.

Related case studies.

All projects
Brierley Hill
View project

Brierley Hill

Infrastructure & civil engineering·£6.73M·Brierley Hill

Dudley Metropolitan Borough Council appointed McPhillips as principal contractor to deliver comprehensive public realm improvements…

York’s Bridge
View project

York’s Bridge

Infrastructure & civil engineering·£5.14M·Pelsall

A new 40m two-way bridge with dedicated pedestrian access and improved visibility and lighting, delivered around ecological and heritage…

Blackheath town centre and bus interchange
View project

Blackheath town centre and bus interchange

Infrastructure & civil engineering·£1.35M·Blackheath

A £1.35M town-centre bus interchange and public realm, delivered on time and on budget with zero RIDDOR incidents and zero service strikes.

60
Years · Est. 1964
McPhillips team planting trees with local schoolchildren

Building with purpose

60+ years of supporting you.

Over six decades we’ve shaped countless communities and built spaces they can be proud of. Explore the McPhillips’ Way – the people behind our projects and the principles that drive us.

Click to access the login or register cheese