This contract involved the design & build of a new five storey 68 room Travelodge Hotel along with 1000m2 of retail shell and 1100m2 of high quality public realm in Telford Town Centre during 2017- 18. The project was secured through competitive tender and following this was delivered with novation of the client’s architect.
CFA piling with pile caps was required for foundations and a 350mm reinforced concrete raft slab was cast.
The ground floor used a steel frame with podium deck and the upper floors were a closed system timber frame with acoustic floating floors.
Composite flat panel cladding was Kingspan Benchmark with a trapezoidal built-up system roof and aluminium double glazed windows were used.
Off-site manufactured bathroom/shower pods were installed and all bedrooms have air conditioning with air-source heat pumps. High efficiency boilers and two CHP plants provide hot water and electricity. Two pre-cast concrete lift shafts were constructed for personnel lifts.
Externally 1100m2 of public realm used Irish Blue Limestone and a 25 jet programmable water fountain has been installed complete with feature lighting wands and misting systems. Planters, benches etc. completed the external works.
McPhillips was the principal contractor for the delivery of a drive- thru Costa Coffee on the outskirts of Ludlow.
Four robust new industrial units (~5,100m²) with gantry cranes and ~6,600m² of concrete yards, delivered on constrained ground with…
A completed and handed-over 12,000 sq ft unit — steel frame, composite cladding, glazed curtain walling and solar PV — for a local timber…