involved constructing a new 1200mm diameter culvert complete with 2x vegetated bag headwall system using the RootLok system, replacing the existing culvert. In addition, the Woodland Trust required construction of a new stone vehicle access track approximately 450m long to access various parts of the woodland together with a 90m² stone car park.
The challenge The scheme presented significant challenges given that works were undertaken within a site designated as ancient woodland.
Development of detailed traffic and pedestrian management plan was required to mitigate traffic congestion at site access whilst maintaining pedestrian access at key rights of way traversing the site that had to remain open. And a high-pressure gas main across the site required careful management and liaison with utility providers.
Protection of ancient woodland tree roots across the area demanded specialised construction techniques and careful material selection: protection of woodland ecology was paramount, necessitating strict environmental controls and monitoring protocols.
Flood risk during periods of prolonged rainfall presented ongoing operational challenges and pollution risk to sensitive woodland watercourses and fauna demanded control measures including silt management and fuel handling protocols. Working within a live watercourse without over-pumping due to ecological constraints imposed significant technical limitations on construction methodology, requiring innovative solutions to manage water flow and silt disturbance.
The solution McPhillips developed comprehensive solutions addressing the complex environmental and infrastructural challenges through proactive planning and strong environmental controls.
Careful traffic coordination phased material deliveries outside peak traffic resulting in no local traffic disruption with local supply partners managed efficiently. While localised ‘no dig’ construction techniques were employed together with strengthened passing points incorporated into the access road to protect and preserve tree root zones close to the surface.
Tree-friendly aggregates with no history of ancient woodland disputes were utilised throughout the project.
Phased culvert construction utilised temporary open ditch diversion to mitigate silt disturbance whilst maintaining existing fauna and flora. Localised weather monitoring allowed for works scheduling within drier periods, optimising site conditions.
Detailed utility surveys and liaison with Cadent Gas included plant exclusion zones and advance protection mat installations.
Gate marshals were provided at all rights of way crossing points with clear pedestrian-friendly signage ensuring public safety.
Comprehensive pollution control included downstream silt nets and bunds, off-site designated refuelling zones utilising HVO fuel rather than diesel, and strict environmental monitoring in accordance with ISO 14001 accredited procedures.