Notice: Function WP_Scripts::add was called incorrectly. The script with the handle "twentysixteen-script" was enqueued with dependencies that are not registered: jquery. Please see Debugging in WordPress for more information. (This message was added in version 6.9.1.) in /home/mcphillipsco/public_html/wp-includes/functions.php on line 6131

Dogs Trust Cardiff progress

The latest footage from Dogs Trust Cardiff shows good progress on the project for the construction of a new £13.5m rehoming centre in the Welsh capital.

Concrete slabs have been constructed and steelwork erected for the rehoming building and SFS for the stray & reclaim building.  Sheet steel has being laid in the rehoming building in preparation for the concrete pours which will form the composite first floor.

The external works are continuing with prepping for the dog runs and continuation of the access road up to binder which will be a useful addition to the site with winter approaching.