Notice: Function WP_Scripts::add was called incorrectly. The script with the handle "twentysixteen-script" was enqueued with dependencies that are not registered: jquery. Please see Debugging in WordPress for more information. (This message was added in version 6.9.1.) in /home/mcphillipsco/public_html/wp-includes/functions.php on line 6131

Talbot Park, Kidderminster

Overview 

The Worcester Street Urban Park Connectivity Project in Kidderminster town centre formed a central element of the wider Kidderminster town centre regeneration programme supported by £20.5 million secured through the Future High Streets Fund. 

The project replaced the former stepped access with a new landscaped green community space, featuring winding footways linking Worcester Street, Bromsgrove Street car park, and the adjacent Lion Fields development.  

The scheme incorporates a dedicated play area, improved disabled access throughout, new LED lighting, high-quality paving, extensive landscaping, and street furniture including modern benches. Section 278 highway works were also completed on Worcester Street and Prospect Hill in collaboration with Worcestershire County Council. 

 Challenges 

The project presented multiple complex technical, logistical and site-specific challenges.  

Legacy demolition materials from previous buildings left significant volumes of demolition arisings requiring identification, excavation, removal and appropriate disposal or re-engineering before construction could progress.  

During excavation, an unknown underground concrete structure was encountered requiring careful assessment, partial removal and redesign of works in some areas. Several large reinforced concrete blocks were discovered beneath the surface as remnants of previous developments, requiring specialist removal methods and additional plant and careful sequencing without affecting surrounding ground stability. Deep drainage infrastructure required installation at depths of up to approximately eight metres below ground level, necessitating extensive excavation support, robust safety controls, complex temporary works designs, and specialist tunnelling contractors delivering underground timber heading frames to connect to existing highway drainage without disruptive surface-level works.  

The steep site gradient created significant compaction challenges during earthworks. Structural risks to adjacent buildings including the neighbouring Sense retail unit required continuous monitoring including tilt sensors and settlement gauges throughout construction. The constrained town centre location with limited material storage space required careful logistics planning and just-in-time delivery strategies. An existing high-voltage underground electrical substation required demolition, relocation and re-waterproofing using a RENOLIT ALKORPLAN F waterproofing membrane system with a 10-year guarantee, requiring constant coordination with National Grid and the client throughout. 

 Our approach 

McPhillips adopted a proactive and innovative approach addressing each challenge systematically.  

  • An AI-equipped drone survey measured site volumes accurately, cross-checked against traditional engineers’ surveys, determining sufficient material was available on site to complete infill works without importing additional aggregates.  
  • Approximately 4,000 tonnes of concrete was crushed and reused as 6F2 capping material, with 85% of all site materials recycled or reused, totalling 8,000m² of an overall 10,000m³ requirement, significantly reducing waste to landfill and vehicle movements.  
  • Drainage systems were constructed progressively as ground was built up, integrating deep drainage runs seamlessly into fill layers.  
  • Specialist tunnelling contractors hand-excavated a 6-metre-deep, 15-metre-long tunnel through sandstone to connect drainage to the existing storm drain, avoiding road closures and maintaining normal town centre activity.  
  • A 14-tonne rear-heel-driven roller enabled precise compaction on steep gradients. Precast L-shaped wall units protected the adjacent Sense retail unit from ground pressure, manufactured off-site for precise quality control and rapid installation.  
  • Tilt monitoring on adjacent buildings with pre-commencement dilapidation surveys provided real-time structural safety assurance.  
  • Comprehensive dust management including water suppression systems, stockpile covering and road cleaning protected the public.  
  • A Section 61 notice managed noise emissions formally throughout construction.  
  • A full suite of SHEQ documentation was maintained including Construction Phase Health & Safety Plan, Risk Assessments and Method Statements, Environmental Management Plan, Confined Space Entry Procedures, and Permit to Work systems, with 34 early warnings and 76 compensation event notifications raised and managed in accordance with NEC procedures. 

 Outcomes 

The project was delivered on programme and within the agreed budget, achieving a defect-free handover and full compliance with all project KPIs. The innovative material reuse strategy recycled 85% of all site materials, delivering significant environmental and cost benefits.  

The specialist tunnelling approach successfully connected drainage infrastructure without road closures or disruption to town centre businesses.  

Strong and collaborative working relationships were established with Wyre Forest District Council, NEC project management team Arcadis, structural designers McBains and landscape architects Ares Landscape Architects, creating a benchmark for future regeneration initiatives in Kidderminster.  

 TESTIMONIAL 

Nadia Kaminska, Regeneration Manager for Wyre Forest District Council: “McPhillips brought a practical, solutions-led approach to a unique project that required flexibility and constant coordination. Working within a constrained environment, they navigated technical and logistical challenges whilst remaining consistently constructive and focused on delivery. 

“A key strength of McPhillips is their approach to challenges. Rather than becoming defensive, they engage early, take ownership, and work collaboratively to find solutions. This attitude made a tangible difference in maintaining progress and resolving issues efficiently. 

“They are approachable, responsive, and easy to work with, which has resulted in a strong and positive working relationship with Wyre Forest District Council. The result is a high-quality public space that reflects not just technical capability, but also a contractor genuinely committed to making projects succeed.” 

Contact Us    More Projects

Project Images

Contact Us